The work started Monday morning and the posts were erected. the "A" frames had already been fabricated and delivered.
The roof frames seemed to fly up, respect to the guys who work for Rened for their skill.

No sooner had the timber frame been completed than the roof went on - all this in ONE week!

 


By the end of Monday 29th the walls are up - well the main bits are and only 8 days
since the work started. All the buildings have a veranda to provide shelter from sun
and the rain. There is also a water collection system on some of the buildings